PROGRESS REPORT FYP2 (W17)

Week: 17 Date: 31st May 2021 - 4th June 2021 Activity:  Project Presentation & Demonstration Day Submission of Technical Paper, Thesis Report and Progress Report Objective: To present and demonstrate my Final Year Project To submit the technical paper and thesis hardcover to UniKL BMI Library To submit claim of FYP materials to Finance Department  Content: Presentation Day was done thru Microsoft Teams platform at 11am. The recorded video presentation was presented to the assessors, followed by the demonstration video of the project. After the demonstration video, there was a QnA session where the assessors were asking questions and further explanation regarding the project.  The whole presentation took about 30 minutes to finish. I was able to answer all questions from the assessors and ended the presentation well. Few improvements can be added into my project such as: Adding a flowmeter to to measure the volume of air that goes into the patient. Since it i...

PROGRESS REPORT FYP2 (W16)

Image
Week: 16 Date:  24th May 2021 - 28th May 2021 Activity:  Final preparation for Project Presentation & Demonstration next week. Completion of working of project. Objective: To complete the working of project and record a video for demonstration. To submit the presentation video and demonstration video on Microsoft Teams. To submit the thesis draft report to SV for checking. Content: The reading of time taken were recorded to test the functionality of the device. It was repeated a few times and measurements were taken for analysis.  Result:  The time taken for the device to  pump the ambu bag for the rate of 10bpm is 58.47 seconds, while for the rate of 15bpm is 58.76 seconds. Lastly, the time taken for the rate of 20bpm is 59.63seconds.                                                               Vide...

PROGRESS REPORT FYP2 (W15)

Week: 15 Date : 17th May 2021 - 21st May 2021 Activity:  Completion of project Meeting with Supervisor Objective: To update about my current progress before the presentation day to my SV. To finish making the project. Content: The meeting was done through Microsoft Teams platform at 10am, and I presented my current progress of the project that I have made before I went back for Hari Raya holiday. The project has been 90% assembled, only left is to put the arm to pump the ambu bag. The development of the project is completed and the functionality of the device was tested. Result:  It was found that the arm could not pump 1/3 of the ambu bag as it should because of the size of the gear on the motor is small hence it should be changed to a larger gear. But unfortunately, I was not able to do it since my project was left at the hostel and I was able to go back to campus when suddenly BMI announced a sudden lockdown due to the increase number of Covid-19 cases.  Conclusio...

PROGRESS REPORT FYP2 (W14)

Image
Week: 14 Date: 10th May  2021 - 14th May 2021 Activity:  To finalize the results Thesis writing on Chapter 4 & Chapter 5 Preparing slide for presentation Objective: To verify and check the accuracy of the project To complete thesis writing Content: Another reliability test was done to check the accuracy of the device. The time taken for 3 tests was repeated for each speed. This is to show that the device is reliable to be used to patients as the time taken ranges between the allowed limit. If the device fail to pump the ambu bag within the set time, it means that there is something wrong with the device and should be checked Result:  All time taken falls accordingly Conclusion:  As a conclusion, the reliability test was done and the device is functioning well. Slide has been prepared for presentation.

PROGRESS REPORT FYP2 (W13)

Image
Week: 13 Date: 3rd May 2021 - 7th May 2021 Activity:  Collecting results Writing Chapter 4 Objective: To get the results form the project To start writing Chapter 4 in thesis Content: The new time delay has been set according to the rate of breathing 10bpm - delay: 16 15bpm -  delay: 10 20bpm - delay: 8 After changing the time delay, time taken for 10 cycles were recorded to measure its accuracy.  Then, it was tested to rotate within a minute and the number of pumping were recorded according to the speed.  Low: 10 pumping Medium: 15 pumping High: 20 pumping Result:  Time taken for Low speed to complete 10 cycle is 58.62s, Medium speed is 39.36s and High speed is 29.10s.  Conclusion:  As a conclusion, the device is able to pump the ambu bag according tomthe rate of breathing of the patient.